All work must be scheduled 5 business days in advance

Contractors must be escorted by building staff at all times

No material storage anywhere in the building

Stairwells are not available for contractor use

All vendors & outside workers require proof of insurance and management approval before entry

Project Timeline

Elevator Shutdown Schedule

Last updated: March 11, 2026

Important: All dates beyond March 9th are estimates. Each elevator modernization is projected to take 8–14 weeks. Timelines are subject to change based on project progress. This page will be updated as the project advances.

Automatic Passenger Elevator

1P7958
Offline Now
Offline: March 9, 2026
Return: Estimated 8–14 weeks from start date
Confirmed offline. This is the first elevator to be modernized.

Service Elevator

1P7960
Scheduled
Offline: Estimated: Early May 2026
Return: Estimated 8–14 weeks from start
During this blackout period, no large deliveries or debris removal will be permitted. Light work and hand-carried materials only.

Manual Passenger Elevator

1P7959
Scheduled
Offline: Estimated: Early July 2026
Return: Estimated 8–14 weeks from start
Scheduling will be confirmed as the project progresses.
Shareholder FAQ

Frequently Asked Questions

Answers to the most common questions about the elevator modernization project.