Project Timeline
Elevator Shutdown Schedule
Last updated: March 11, 2026
Important: All dates beyond March 9th are estimates. Each elevator modernization is projected to take 8–14 weeks. Timelines are subject to change based on project progress. This page will be updated as the project advances.
Automatic Passenger Elevator
1P7958
Offline: March 9, 2026
Return: Estimated 8–14 weeks from start date
Confirmed offline. This is the first elevator to be modernized.
Service Elevator
1P7960
Offline: Estimated: Early May 2026
Return: Estimated 8–14 weeks from start
During this blackout period, no large deliveries or debris removal will be permitted. Light work and hand-carried materials only.
Manual Passenger Elevator
1P7959
Offline: Estimated: Early July 2026
Return: Estimated 8–14 weeks from start
Scheduling will be confirmed as the project progresses.